Categories BLOG Day 44, 3/25 Post author By dannykaskel Post date March 27, 2017 No Comments on Day 44, 3/25 Stripping
Categories BLOG Day 43, 3/24 Post author By dannykaskel Post date March 27, 2017 No Comments on Day 43, 3/24 Roof truss delivery, final concrete pour- roof beams overhang/ eyebrows
Categories BLOG Day 42, 3/23 Post author By dannykaskel Post date March 27, 2017 No Comments on Day 42, 3/23 Finish forming & tying, Building inspections
Categories BLOG Day 40-41, March 21-22 Post author By dannykaskel Post date March 22, 2017 No Comments on Day 40-41, March 21-22 Continue re-bar for roof beams and overhangs/ eyebrows, finish forming roof beams
Categories BLOG Day 40, 3/20 Post author By dannykaskel Post date March 21, 2017 No Comments on Day 40, 3/20 Begin re-bar for roof beams and overhangs/ eyebrows
Categories BLOG Day 39, March 19 Post author By dannykaskel Post date March 21, 2017 No Comments on Day 39, March 19 A day of rest
Categories BLOG Day 38, March 18 Post author By dannykaskel Post date March 19, 2017 No Comments on Day 38, March 18 Re-bar delivery, Continue forming roof beams, continue scaffolding for eyebrows and overhang nude selfie Soledad
Categories BLOG Day 37, March 17 Post author By dannykaskel Post date March 19, 2017 No Comments on Day 37, March 17 Continue forming roof beams and eyebrows, continue scaffolding for eyebrows and overhang, finish interior bearing wall headers
Categories BLOG Day 36, March 16 Post author By dannykaskel Post date March 17, 2017 No Comments on Day 36, March 16 Continue forming roof beams, continue scaffolding for eyebrows and overhang bhad bhabie xxx
Categories BLOG Day 35, March 15 Post author By dannykaskel Post date March 17, 2017 No Comments on Day 35, March 15 Continue forming roof beams, begin scaffolding for eyebrows and overhang