Categories BLOG Day 72, Saturday, April 22 Post author By dannykaskel Post date April 24, 2017 No Comments on Day 72, Saturday, April 22 Bathroom ceiling framing, knee wall framing for kitchen island, continue electrical rough-in’s
Categories BLOG Day 71, Friday, April 21 Post author By dannykaskel Post date April 24, 2017 No Comments on Day 71, Friday, April 21 Continue plumbing and electrical Rough-in’s
Categories BLOG Day 66-70, April 16-20 Post author By dannykaskel Post date April 21, 2017 No Comments on Day 66-70, April 16-20 Window bucks and water proofing, begin plumbing rough-in and top out, continue mechanical and electrical rough-in, scaffolding pick up
Categories BLOG Day 65, Saturday April 15 Post author By dannykaskel Post date April 16, 2017 No Comments on Day 65, Saturday April 15 Continue electrical rough-in, continue waterproofing window openings
Categories BLOG Day 64, Friday April 14 Post author By dannykaskel Post date April 16, 2017 No Comments on Day 64, Friday April 14 Continue mechanical rough-in, water proofing window openings
Categories BLOG Day 62-63, April 12-13 Post author By dannykaskel Post date April 14, 2017 No Comments on Day 62-63, April 12-13 Stripping eyebrows/ overhangs/ beams, begin mechanical rough in, BBQ
Categories BLOG Day 61, April 11 Post author By dannykaskel Post date April 14, 2017 No Comments on Day 61, April 11 Continue electrical rough in
Categories BLOG Day 60, April 10 Post author By dannykaskel Post date April 14, 2017 No Comments on Day 60, April 10 Cleaning day, final coat of roof protection
Categories BLOG Day 58-59, April 8-9 Post author By dannykaskel Post date April 12, 2017 No Comments on Day 58-59, April 8-9 Begin elec rough-in
Categories BLOG Day 54-57, April 4-7 Post author By dannykaskel Post date April 9, 2017 No Comments on Day 54-57, April 4-7 jasmine91 devon shae nude Begin framing interior metal partitions, continue roof, roof inspections , concrete eyebrows