Day 6, Feb 14

Poured footers, block delivery 

Categories
BLOG

Day 5, Feb 13

Pass foundation inspection, floating meter set up/installation, electrical grounding install, soil soak in preparation for pouring concrete footers

corinna kopf instagram


Categories
BLOG

Day 4, Feb 12

Day of rest

Categories
BLOG

Day 3, Feb 11

Temporary fence, continue re-bar – dowels, ties, corners, chairs — foundation inspection Monday

Categories
BLOG

Day 2, Feb 10

Finish excavating footers, begin compaction and bottom chord rebar, portable toilet delivery, floating meter set up

Categories
BLOG

Day 1 – Construction Commencement- Thursday, February 9th, 2017

Footers, re-bar delivery, site set-up

Categories
BLOG

Building Permit

February 8th, 2017

Categories
BLOG

Pre construction meeting and building corner survey points

Categories
BLOG

Construction Document Plan Review Underway

Wednesday, July 13th, 2016: Architect signs & seals plans + construction documents submitted to municipality for processing (pleasant experience with the permit clerks!)= milestone moment