Day 6, Feb 14

Poured footers, block delivery 

Categories
BLOG

Day 5, Feb 13

Pass foundation inspection, floating meter set up/installation, electrical grounding install, soil soak in preparation for pouring concrete footers


Categories
BLOG

Day 4, Feb 12

Day of rest

Categories
BLOG

Day 3, Feb 11

Temporary fence, continue re-bar – dowels, ties, corners, chairs — foundation inspection Monday

Categories
BLOG

Day 2, Feb 10

Finish excavating footers, begin compaction and bottom chord rebar, portable toilet delivery, floating meter set up

Categories
BLOG

Day 1 – Construction Commencement- Thursday, February 9th, 2017

Footers, re-bar delivery, site set-up

Categories
BLOG

Building Permit

February 8th, 2017

Categories
BLOG

Pre construction meeting and building corner survey points

Categories
BLOG

Construction Document Plan Review Underway

Wednesday, July 13th, 2016: Architect signs & seals plans + construction documents submitted to municipality for processing (pleasant experience with the permit clerks!)= milestone moment