Categories BLOG Day 19, Feb 27 Post author By dannykaskel Post date February 28, 2017 No Comments on Day 19, Feb 27 First lift CMU
Categories BLOG Day 18, Feb 26 Post author By dannykaskel Post date February 27, 2017 No Comments on Day 18, Feb 26 Concrete curing
Categories BLOG Day 17, Feb 25 Post author By dannykaskel Post date February 27, 2017 No Comments on Day 17, Feb 25 S.O.G
Categories BLOG Day 16, Feb 24 Post author By dannykaskel Post date February 25, 2017 No Comments on Day 16, Feb 24 Finish prep for Slab
Categories BLOG Day 15, Feb 23 Post author By dannykaskel Post date February 23, 2017 No Comments on Day 15, Feb 23 Begin preperation for slab on grade, soil compaction tests, building inspection – pass
Categories BLOG Day 14, Feb 22 Post author By dannykaskel Post date February 23, 2017 No Comments on Day 14, Feb 22 Passed electrical and plumbing inspections, backfill, termite spray, and a lot of rain
Categories BLOG Day 13, Feb 21 Post author By dannykaskel Post date February 23, 2017 No Comments on Day 13, Feb 21 Underground electrical begin, slab material delivery
Categories BLOG Day 12, Feb 20 Post author By dannykaskel Post date February 21, 2017 No Comments on Day 12, Feb 20 Underground plumbing
Categories BLOG Day 11, Feb 19 Post author By dannykaskel Post date February 20, 2017 No Comments on Day 11, Feb 19 Sunday= A day a rest
Categories BLOG Day 10, Feb 18 Post author By dannykaskel Post date February 20, 2017 No Comments on Day 10, Feb 18 Temp power set up, bobcat –earthwork, prep for underground rough in’s