Categories
BLOG

Day 10, Feb 18

Temp power set up, bobcat –earthwork, prep for underground rough in’s

Categories
BLOG

Day 9, Feb 17

Crushed Lime rock delivery, raise building pad & compaction!

Categories
BLOG

Day 8, Feb 16 

Storage shed, prepare for filled cell pour – form columns, tie re bar, 4 yard, 5000 psi, regular slum, pump mix concrete pour – filled cells, lime rock delivery 

Categories
BLOG

Day 7, Feb 15

Layout block for masons, begin laying block – stem wall, Block outs –> 838 cinder blocks// 8 hrs// 2 masons, one helper

Categories
BLOG

Day 6, Feb 14

Poured footers, block delivery 

Categories
BLOG

Day 5, Feb 13

Pass foundation inspection, floating meter set up/installation, electrical grounding install, soil soak in preparation for pouring concrete footers

corinna kopf instagram


Categories
BLOG

Day 4, Feb 12

Day of rest

Categories
BLOG

Day 3, Feb 11

Temporary fence, continue re-bar – dowels, ties, corners, chairs — foundation inspection Monday

Categories
BLOG

Day 2, Feb 10

Finish excavating footers, begin compaction and bottom chord rebar, portable toilet delivery, floating meter set up

Categories
BLOG

Day 1 – Construction Commencement- Thursday, February 9th, 2017

Footers, re-bar delivery, site set-up