Day 9, Feb 17

Crushed Lime rock delivery, raise building pad & compaction!

Categories
BLOG

Day 8, Feb 16 

Storage shed, prepare for filled cell pour – form columns, tie re bar, 4 yard, 5000 psi, regular slum, pump mix concrete pour – filled cells, lime rock delivery 

Categories
BLOG

Day 7, Feb 15

Layout block for masons, begin laying block – stem wall, Block outs –> 838 cinder blocks// 8 hrs// 2 masons, one helper

Categories
BLOG

Day 6, Feb 14

Poured footers, block delivery 

Categories
BLOG

Day 5, Feb 13

Pass foundation inspection, floating meter set up/installation, electrical grounding install, soil soak in preparation for pouring concrete footers


Categories
BLOG

Day 4, Feb 12

Day of rest

Categories
BLOG

Day 3, Feb 11

Temporary fence, continue re-bar – dowels, ties, corners, chairs — foundation inspection Monday

Categories
BLOG

Day 2, Feb 10

Finish excavating footers, begin compaction and bottom chord rebar, portable toilet delivery, floating meter set up

Categories
BLOG

Day 1 – Construction Commencement- Thursday, February 9th, 2017

Footers, re-bar delivery, site set-up

Categories
BLOG

Building Permit

February 8th, 2017