Day 95- 99: Monday, May 15- Friday, May 19

Finish stucco, finish fi foil & mineral wool insulation + open cell spray foam+ inspection, Sheetrock deliver, begin drywall, roll off dumpster swap, eddy clean, compete MEP rough-in inspections, finish window and door trim/ caulking

Categories
BLOG

Day 94: Sunday, May 14

A day of rest + Mother’s Day 

Categories
BLOG

Day 89-93: Tuesday, May 9-Saturday, May 13

Begin stucco scratch and final coats, plumbing rough-in top out inspection, low voltage inspection, electrical feeder wire trench/ conduit connection, begin insulation, window/ door inspection , finishing framing, framing inspection

Categories
BLOG

Day 88, Monday, May 8

Finish plumbing rough-in, XVent seal/ caulk, finish low voltage rough-in, finish window install

Categories
BLOG

Day 87, Sunday, May 7

A day of rest

Categories
BLOG

Day 86, Saturday, May 6

Ceiling framing, cross bracing floor trusses, backing for kitchen cabinets and shower panels, continue plumbing rough-in– shower pans, mechanical rough-in corrections

Categories
BLOG

Day 81-85: Monday, May 1- Friday, May 5

Finish mechanical rough-in, continue windows and doors installation, plumbing, low-voltage, framing, begin stucco, Eddy sweep and clean, FPL materials pick up 

Categories
BLOG

Day 80, Sunday April 30

A day of rest

Categories
BLOG

Day 78-79, fri& sat, April 28-29

Continue window install, begin low-voltage, finish waterproofing, continue plumbing rough-in


Categories
BLOG

Day 77, Thursday, April 27

Underground trench for Elec, communications  service, finish mechanical rough-in, begin glazing– front door install