Day 81-85: Monday, May 1- Friday, May 5

Finish mechanical rough-in, continue windows and doors installation, plumbing, low-voltage, framing, begin stucco, Eddy sweep and clean, FPL materials pick up 

Categories
BLOG

Day 80, Sunday April 30

A day of rest

Categories
BLOG

Day 78-79, fri& sat, April 28-29

Continue window install, begin low-voltage, finish waterproofing, continue plumbing rough-in


Categories
BLOG

Day 77, Thursday, April 27

Underground trench for Elec, communications  service, finish mechanical rough-in, begin glazing– front door install

Categories
BLOG

Day 76, Wednesday April 26

Electrical rough-in & wood bucking inspections, continue mechanical rough-in

Categories
BLOG

Day 75, Tuesday April 25

XVent penetrations, dumpster delivery 

Categories
BLOG

Day 74, Monday April 24

Continue electrical & plumbing rough-in, call for utility locates

Categories
BLOG

Day 73, Sunday, April 23

Continue electrical rough in

Categories
BLOG

Day 72, Saturday, April 22

Bathroom ceiling framing, knee wall framing for kitchen island, continue electrical rough-in’s

Categories
BLOG

Day 71, Friday, April 21

Continue plumbing and electrical Rough-in’s