Sunday,  June 4: Day 116

A day of rest

Categories
BLOG

Day 109-115: Monday, May 29- Saturday, June 3

Begin flooring, begin painting, site clean up/ backfill elec/ lv trench, Comcast service install

Categories
BLOG

Day 108, Sunday May 28

A day of rest

Categories
BLOG

Day: 100-107: Saturday, May 20- Saturday, May 27

Begin/Finish hanging drywall, finishing drywall, Water service line tap/ meter box, eddy clean, elec/ low voltage service line conduit connections, import fill for septic drain field, begin tile/ flooring, screw inspection, finish insulation 

Categories
BLOG

Day 95- 99: Monday, May 15- Friday, May 19

Finish stucco, finish fi foil & mineral wool insulation + open cell spray foam+ inspection, Sheetrock deliver, begin drywall, roll off dumpster swap, eddy clean, compete MEP rough-in inspections, finish window and door trim/ caulking

Categories
BLOG

Day 94: Sunday, May 14

A day of rest + Mother’s Day 

onlyfans porn spicymum24

Categories
BLOG

Day 89-93: Tuesday, May 9-Saturday, May 13

Begin stucco scratch and final coats, plumbing rough-in top out inspection, low voltage inspection, electrical feeder wire trench/ conduit connection, begin insulation, window/ door inspection , finishing framing, framing inspection

Categories
BLOG

Day 88, Monday, May 8

Finish plumbing rough-in, XVent seal/ caulk, finish low voltage rough-in, finish window install

Categories
BLOG

Day 87, Sunday, May 7

A day of rest

Categories
BLOG

Day 86, Saturday, May 6

Ceiling framing, cross bracing floor trusses, backing for kitchen cabinets and shower panels, continue plumbing rough-in– shower pans, mechanical rough-in corrections