Categories BLOG Day 36, March 16 Post author By dannykaskel Post date March 17, 2017 No Comments on Day 36, March 16 Continue forming roof beams, continue scaffolding for eyebrows and overhang
Categories BLOG Day 35, March 15 Post author By dannykaskel Post date March 17, 2017 No Comments on Day 35, March 15 Continue forming roof beams, begin scaffolding for eyebrows and overhang
Categories BLOG Day 34, March 14 Post author By dannykaskel Post date March 15, 2017 No Comments on Day 34, March 14 Begin forming roof beams, job site clean up
Categories BLOG Day 33, March 13 Post author By dannykaskel Post date March 14, 2017 No Comments on Day 33, March 13
Categories BLOG Day 32, March 12 Post author By dannykaskel Post date March 14, 2017 No Comments on Day 32, March 12 A day of rest
Categories BLOG Day 31, March 11 Post author By dannykaskel Post date March 13, 2017 No Comments on Day 31, March 11 Continue sheathing, ledger bolts and straps, block delivery
Categories BLOG Day 30, March 10 Post author By dannykaskel Post date March 11, 2017 No Comments on Day 30, March 10 Begin sheathing — 3/4″ ply tounge and groove
Categories BLOG Day 29, March 9 Post author By dannykaskel Post date March 10, 2017 No Comments on Day 29, March 9 Floor truss and ledger installation, FFE and tie beam elevation survey points
Categories BLOG Day 28, March 8 Post author By dannykaskel Post date March 9, 2017 No Comments on Day 28, March 8 Truss and sheathing delivery, 2×6 wood bearing wall’s
Categories BLOG Day 27, March 7 Post author By dannykaskel Post date March 8, 2017 No Comments on Day 27, March 7 Slab inspection, concrete– pour tie beams, slabs, landings, and stairs — begin stripping