Categories BLOG Day 30, March 10 Post author By dannykaskel Post date March 11, 2017 No Comments on Day 30, March 10 Begin sheathing — 3/4″ ply tounge and groove
Categories BLOG Day 29, March 9 Post author By dannykaskel Post date March 10, 2017 No Comments on Day 29, March 9 Floor truss and ledger installation, FFE and tie beam elevation survey points
Categories BLOG Day 28, March 8 Post author By dannykaskel Post date March 9, 2017 No Comments on Day 28, March 8 Truss and sheathing delivery, 2×6 wood bearing wall’s
Categories BLOG Day 27, March 7 Post author By dannykaskel Post date March 8, 2017 No Comments on Day 27, March 7 Slab inspection, concrete– pour tie beams, slabs, landings, and stairs — begin stripping
Categories BLOG Day 26, March 6 Post author By dannykaskel Post date March 7, 2017 No Comments on Day 26, March 6 Continue forming stairs and intermediate slab, tie beam inspection
Categories BLOG Day 25, March 5 Post author By dannykaskel Post date March 5, 2017 No Comments on Day 25, March 5 A day of rest and a special family visit kbalpha85 bickett real name
Categories BLOG Day 24, March 4 Post author By dannykaskel Post date March 5, 2017 No Comments on Day 24, March 4 Continue forming tie beams, stairs, landings, slabs
Categories BLOG Day 23, March 3 Post author By dannykaskel Post date March 3, 2017 No Comments on Day 23, March 3 Continue forming tie beams –rebar
Categories BLOG Day 22, March 2 Post author By dannykaskel Post date March 3, 2017 No Comments on Day 22, March 2 Continue forming tie beams and first run of stairs, portable toilet service, re bar delivery
Categories BLOG Day 21, March 1 Post author By dannykaskel Post date March 2, 2017 No Comments on Day 21, March 1 Begin forming tie beams, FPL temp power