Day 16, Feb 24

Finish prep for Slab

Categories
BLOG

Day 15, Feb 23

Begin preperation for slab on grade, soil compaction tests, building inspection – pass

Categories
BLOG

Day 14, Feb 22

Passed electrical and plumbing inspections, backfill, termite spray, and a lot of rain

Categories
BLOG

Day 13, Feb 21

Underground electrical begin, slab material delivery 

Categories
BLOG

Day 12, Feb 20

Underground plumbing

Categories
BLOG

Day 11, Feb 19

Sunday= A day a rest 

Categories
BLOG

Day 10, Feb 18

Temp power set up, bobcat –earthwork, prep for underground rough in’s

Categories
BLOG

Day 9, Feb 17

Crushed Lime rock delivery, raise building pad & compaction!

Categories
BLOG

Day 8, Feb 16 

Storage shed, prepare for filled cell pour – form columns, tie re bar, 4 yard, 5000 psi, regular slum, pump mix concrete pour – filled cells, lime rock delivery 

Categories
BLOG

Day 7, Feb 15

Layout block for masons, begin laying block – stem wall, Block outs –> 838 cinder blocks// 8 hrs// 2 masons, one helper